| Task Name | Duration | Start | Finish | Resource Names |
| DeForest Williamsburg Way | 52 days | Wed 8/5/26 | Thu 10/15/26 | |
| Traffic Control Williamsburg | 1 day | Wed 8/5/26 | Wed 8/5/26 | Midstate Traffic |
| Erosion Control Williamsburg | 1 day | Wed 8/5/26 | Wed 8/5/26 | Westland |
| Sawcutting Williamsburg | 1 day | Wed 8/5/26 | Wed 8/5/26 | ASTI |
| Clear and grub Williamsburg | 1 day | Thu 8/6/26 | Thu 8/6/26 | S&L Misc |
| Strip topsoil Williamsburg | 2 days | Wed 8/5/26 | Thu 8/6/26 | S&L Dirt Crew |
| Remove Asphalt Surface Williamsburg | 1 day | Thu 8/6/26 | Thu 8/6/26 | S&L Dirt |
| Remove concrete curb and walks Williamsburg | 1 day | Fri 8/7/26 | Fri 8/7/26 | S&L Dirt |
| Pipe Crew 2 Williamsburg | 7 days | Fri 8/7/26 | Mon 8/17/26 | Pipe Crew 2 |
| Televise sanitary main | 1 day | Tue 8/18/26 | Tue 8/18/26 | Great Lakes |
| Unclassified and Base Course Fair str. | 6 days | Tue 8/18/26 | Tue 8/25/26 | S&L Dirt Crew |
| Concrete curb, pavement, and sidewalk Williamsburg | 14 days | Wed 8/26/26 | Mon 9/14/26 | Cattell |
| Backfill Curbs Williamsburg | 1 day | Tue 9/15/26 | Tue 9/15/26 | S&L Misc |
| Topsoil placement Williamsburg | 3 days | Wed 9/16/26 | Fri 9/18/26 | S&L Misc |
| Install RRFB Williamsburg | 1 day | Fri 9/18/26 | Fri 9/18/26 | Ark Electric |
| Landscape restoration Williamsburg | 3 days | Mon 9/21/26 | Wed 9/23/26 | Westland |
| Road sign installation Williamsburg | 2 days | Thu 9/24/26 | Fri 9/25/26 | Westland |
| Finish Road Base Williamsburg | 1 day | Thu 9/24/26 | Thu 9/24/26 | S&L Dirt Crew |
| Casting adjustments Williamsburg | 2 days | Fri 9/25/26 | Mon 9/28/26 | S&L Misc Crew |
| Asphalt Paving Williamsburg | 2 days | Tue 9/29/26 | Wed 9/30/26 | Tri County |
| Pavement Markings Williamsburg | 1 day | Thu 10/1/26 | Thu 10/1/26 | Century Traffic |