Task Name

Duration

Start

Finish

Resource Names

DeForest Williamsburg Way

52 days

Wed 8/5/26

Thu 10/15/26

Traffic Control Williamsburg

1 day

Wed 8/5/26

Wed 8/5/26

Midstate Traffic

Erosion Control Williamsburg

1 day

Wed 8/5/26

Wed 8/5/26

Westland

Sawcutting Williamsburg

1 day

Wed 8/5/26

Wed 8/5/26

ASTI

Clear and grub Williamsburg

1 day

Thu 8/6/26

Thu 8/6/26

S&L Misc

Strip topsoil Williamsburg

2 days

Wed 8/5/26

Thu 8/6/26

S&L Dirt Crew

Remove Asphalt Surface Williamsburg

1 day

Thu 8/6/26

Thu 8/6/26

S&L Dirt

Remove concrete curb and walks Williamsburg

1 day

Fri 8/7/26

Fri 8/7/26

S&L Dirt

Pipe Crew 2 Williamsburg

7 days

Fri 8/7/26

Mon 8/17/26

Pipe Crew 2

Televise sanitary main

1 day

Tue 8/18/26

Tue 8/18/26

Great Lakes

Unclassified and Base Course Fair str.

6 days

Tue 8/18/26

Tue 8/25/26

S&L Dirt Crew

Concrete curb, pavement, and sidewalk Williamsburg

14 days

Wed 8/26/26

Mon 9/14/26

Cattell

Backfill Curbs Williamsburg

1 day

Tue 9/15/26

Tue 9/15/26

S&L Misc

Topsoil placement Williamsburg

3 days

Wed 9/16/26

Fri 9/18/26

S&L Misc

Install RRFB Williamsburg

1 day

Fri 9/18/26

Fri 9/18/26

Ark Electric

Landscape restoration Williamsburg

3 days

Mon 9/21/26

Wed 9/23/26

Westland

Road sign installation Williamsburg

2 days

Thu 9/24/26

Fri 9/25/26

Westland

Finish Road Base Williamsburg

1 day

Thu 9/24/26

Thu 9/24/26

S&L Dirt Crew

Casting adjustments Williamsburg

2 days

Fri 9/25/26

Mon 9/28/26

S&L Misc Crew

Asphalt Paving Williamsburg

2 days

Tue 9/29/26

Wed 9/30/26

Tri County

Pavement Markings Williamsburg

1 day

Thu 10/1/26

Thu 10/1/26

Century Traffic